Construction adjudication deadline calculators

Construction adjudication timing is short and procedure-specific. Start with the notice or referral step and check the adjudication agreement, Scheme provisions and any agreed timetable alongside the result.

Choose a deadline checkHub sources reviewed 7 August 2026. Each rule shows its own date.

Worked check

One tested route from this procedure

Example input
03/08/2026
Relevant fact
The notice of adjudication was given on Monday 3 August 2026.
Expected result
Monday 10 August 2026

The calculator applies the seven-day referral period from the notice. The contractual scheme and any agreed appointment process must still be checked.

Choose the procedure first

A cited route for the step in front of you

These are focused procedural checks, not a general legal guide. Open the named step to see its trigger, period, counting method and the boundary that still needs to be checked.

Check before use

The procedure is not the whole matter

  • Contractual adjudication clauses and agreed extensions can change the timetable.
  • Court proceedings, arbitration and adjudication use different procedural systems.