Construction adjudication deadline
Construction adjudication referral deadline calculator
The referring party must normally refer the dispute to the adjudicator within seven days of giving notice of adjudication. Weekends count, while the specified statutory holidays are excluded.
Rule reviewed
At a glance
What the calculator applies
- Period
- Seven days
- Trigger
- Notice of adjudication
- Direction
- Forward from the notice
- Counting method
- HGCRA day count: weekends count; Christmas Day, Good Friday and bank holidays do not.
Free calculation
Calculate from the relevant date
The jurisdiction, forum and triggering event are preset for this deadline. Enter the date and any facts the calculator asks for.
Find the deadline you need.
Choose an exact deadline result to open it preselected, or choose a court or tribunal.
Loading calculator...
Advanced options · Browse by area of law
Worked check
See what the calculator checks before it produces a date
- Example input
- 03/08/2026
Start with 03/08/2026 as the notice of adjudication. The calculator applies hgcra day count: weekends count; christmas day, good friday and bank holidays do not. and the calculator applies the statutory holiday exclusions for this scheme referral route. before it shows the cited output and the checks that may change it.
Calculation basis
How the date is counted
HGCRA day count: weekends count; Christmas Day, Good Friday and bank holidays do not.
The calculator applies the statutory holiday exclusions for this Scheme referral route.
Check before use
Exceptions and matter facts
- Check whether the contract displaces the Scheme and whether the notice was validly given.
- This is a referral deadline, not the separate adjudicator-decision or payment timetable.
Check this result before using it
Deadline Engine is calculation software, not legal advice. Check the current rule, any order and the facts before adding a date to your diary.
Continue checking