Construction adjudication deadline

Construction adjudicator decision deadline guide

Under the Scheme, an adjudicator must normally reach a decision no later than 28 days after receiving the referral notice. The period becomes 42 days if the referring party consents, and can be longer if the parties agree after notice of adjudication.

Check the source guide

Rule reviewed

At a glance

What this source guide covers

Period
28 days by default; 42 days with referring-party consent; longer by later party agreement
Trigger
Receipt of the referral notice by the adjudicator
Direction
Forward from receipt of the referral notice
Counting method
The statutory default runs from receipt of the referral notice. The 28-day calculator path is useful only where no valid extension has been agreed.

Cited source guide

Check the rule before calculating a date

This route has a real deadline question and a current primary source, but it needs facts or time-counting treatment the existing calculator cannot faithfully collect yet. It deliberately does not generate a date.

Read the primary source

Worked check

See how to check the source before calculating a date

Example input
03/08/2026

Start with 03/08/2026 as the receipt of the referral notice by the adjudicator. The calculator applies the statutory default runs from receipt of the referral notice. the 28-day calculator path is useful only where no valid extension has been agreed. and housing grants, construction and regeneration act 1996, section 116 excludes christmas day, good friday and the relevant bank holidays from the statutory day count. before it shows the cited output and the checks that may change it.

Calculation basis

How the date is counted

The statutory default runs from receipt of the referral notice. The 28-day calculator path is useful only where no valid extension has been agreed.

Housing Grants, Construction and Regeneration Act 1996, section 116 excludes Christmas Day, Good Friday and the relevant bank holidays from the statutory day count.

Check before use

Exceptions and matter facts

  • This is the Scheme default. Check the adjudication provisions of the contract and every consent or agreement extending time.
  • A failure to decide in time has the consequences set out in paragraph 19(2); it does not turn the original date into a safe assumption.

Check this rule before using it

Deadline Engine is calculation software, not legal advice. Check the current rule, any order and the facts before adding a date to your diary.