What is the deadline for action for breach of a contract for the sale of goods?

The period for action for breach of a contract for the sale of goods normally runs 4 years from accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance, under UCC 2-725(1). The period is measured in calendar years.

Calculate my deadline
Period
4 years
Trigger
Accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance
Rule
UCC 2-725(1)
New York Courts rules and legislation

New York rules as encoded, holiday calendar verified

Free calculator · No account needed

Calculate your deadline

Enter the date of accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance. See the date, cited rule and counting steps.

Loading calculator...

Which date starts the 4 years period?

The period runs from the accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance.

Count forward from the trigger event. Confirm the event on the docket or in the service record before entering a date.

"An action for breach of any contract for sale must be commenced within four years after the cause of action has accrued. By the original agreement the parties may reduce the period of limitation to not less than one year but may not extend it." ... "A cause of action accrues when the breach occurs, regardless of the aggrieved party's lack of knowledge of the breach."

UCC 2-725(1)
Read New York Courts rules and legislation
Use the event the rule names.

This period runs from the specific event in the cited rule. Do not substitute a nearby date such as a hearing, a courtesy copy or the day you first learned of it.

Which date do I enter?

How are the 4 years counted?

  1. Exclude the day of the trigger event.
  2. Count every following day, including intermediate Saturdays, Sundays and legal holidays.
  3. If the last day is a Saturday, Sunday or New York legal holiday, continue to the next day that is not one of those.

Exclude the trigger day and count calendar days under General Construction Law 20 (days).

If the final day is a Saturday, Sunday or legal holiday in the New York calendar, the computation rule carries it to the next open day.

New York computes time under General Construction Law 20 (days). The applied calendar bundles the state legal holidays for the covered years; court-specific closures and emergency orders are not bundled.

Read General Construction Law 20 (days)
National rules do not establish local facts.

The calculation gives the ordinary national-rule date. Check relevant holidays, the court’s accessibility and its filing cutoff separately.

Review the filing checklist

What does a worked calculation look like?

Fictitious example

Assume the accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance on Tuesday, September 1, 2026 (accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance on this date, with no order, motion or extension affecting the period), with no order, motion, extension or local closure affecting the result. Exclude the trigger day and count calendar days under General Construction Law 20 (days). The last counted day falls on a weekend or legal holiday, so the deadline moves to the next open day. The example assumes no local rule, order or closure changes the default period.

Example counting steps
StepWhat is countedDate
TriggerDo not count this daySeptember 1, 2026
Period ends4 years measured under the cited ruleSeptember 2, 2030
Example resultMonday, September 2, 2030
Try these dates using the worked-example button

Can an order, motion or extension change the deadline?

Extensions
None by the court. The parties may shorten the period to not less than one year by the original agreement, but may not lengthen it. UCC 2-725(3) preserves the tolling and savings law otherwise applicable.
Orders and local rules
A scheduling order, stipulation approved by the court, standing order or local rule can set a different period and controls over the national default.
  • None by the court. The parties may shorten the period to not less than one year by the original agreement, but may not lengthen it. UCC 2-725(3) preserves the tolling and savings law otherwise applicable.
  • A stipulation, scheduling order, standing order or local rule can set a different period and controls over the national default.

What should I check before filing?

These checks help you review the result. They do not activate a calendar date or certify that the deadline applies.

Common questions

Find answers about when this 4 years period starts, how it is counted, what can change it and how to keep your calculation.

Starting the clock

Does the clock start on the accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance, or when I first learned of it?

The period runs from the accrual, which occurs when the breach occurs regardless of the aggrieved party's lack of knowledge; on tender of delivery for a warranty claim unless the warranty explicitly extends to future performance as the rule defines it, not from the day you read about it, received a courtesy copy or attended a hearing. Use the date shown on the docket or in the service record.

Counting days and filing

Which time zone and filing cutoff apply?

New York filing rules and the court’s electronic filing system set the cutoff. This calculator does not verify filing hours or system availability.

General Construction Law 20 (days)

What if the court is inaccessible on the last day?

General Construction Law 20 (days) and the court’s administrative orders govern an inaccessible clerk’s office. Check the court’s notices. This calculator does not predict a closure.

General Construction Law 20 (days)

Extensions and local rules

Can the court extend this deadline?

None by the court. The parties may shorten the period to not less than one year by the original agreement, but may not lengthen it. UCC 2-725(3) preserves the tolling and savings law otherwise applicable. A request does not itself extend the period, and no discretionary extension is calculated here.

Do local rules, standing orders or a scheduling order change the date?

They can. Many courts set their own periods by local rule, standing order or case-specific order, and those control over the national default. This calculator gives the national-rule date only; compare it with any order in the case before relying on it.

Choosing the right calculator

Does this calculator decide whether the rule applies to my case?

No. It calculates a period from the date you provide under the cited rule. It does not decide whether the rule governs your filing, whether an exception applies, or whether the filing has merit. Those questions need separate review.

Can I calculate the deadline without an account?

Yes. Enter the trigger date to see the free national-rule calculation, citation, counting steps and warnings. You can add court context after the result. Missing court review keeps the result provisional.

Results, records and your case

What is included in an Evidence Record?

The retained inputs, result, cited rule, calculation working, warnings and review state. The PDF includes a payload digest and retained-data appendix, and the record can be verified against its fingerprint later. It records the calculation, not a guarantee of legal correctness.

Does saving to a case activate the calendar?

Not automatically. Provisional records remain subject to review. A separately labeled manual date does not alter the original calculation.

Official sources and review

The period and the counting method come from different provisions. The official source is the court’s published rules; the reading links open the rule text at the Legal Information Institute.

Provisions used in this guide
ProvisionPurpose
UCC 2-725(1)Trigger and period
General Construction Law 20 (days)Counting, holidays and the last day
Read the official New York Courts rules and legislation

Rule record reviewed . Guide sources checked . Next source check .

Published by Deadline Engine. This tool calculates the ordinary period under the cited rule. It does not decide whether the rule applies, obtain an extension or file anything for you.

Cookie preferences

Deadline Engine uses necessary cookies for authentication and security. You can choose whether we may load Plausible Analytics to measure aggregate site use. We do not use advertising or marketing tracking. You can change this any time from the footer. Read the Cookie Policy.